Workpackages

Workpackage 1

Workpackage 2

Workpackage 3

Workpackage 4

Workpackage 5

Deliverable List


 

1

Workpackage WP1 – Project Management

 

Objectives

This Work-package will provide the effort necessary to ensure the appropriate management in order to achieve a high degree of overall performance for the project, and at the same time assessing and evaluating the quality of the results achieved. It will care that the allocated resources for the Work Packages are consistent with the work that will be performed in them. The Project Co-ordinator will go in depth with the following list of important issues:

·         To guarantee the correct progress of the work. and the technical coherence with the specifications.

·         To disseminate and make available the partial and global results of the project, and the documentation generated, to all the partners and to other projects under the same programme by concertation activities.

·         To organise the necessary meetings, workshops, etc, needed for the correct execution of the project.

·         To carry out assessment and evaluation in order to guarantee a high quality in production of the achievements, results, deliverables and other documents

·         To guarantee the good collaboration among all the partners work teams is achieved

Deliverable

 

Title

Date

Nature

Dissemination

D1.1

Guide of project management and comm. facilities

M3

R

CO

D1.2

Produce periodically progress reports (3 months)

M3,6..21

R

CO

D1.3

Final Report

M24

R

PU

 

1

Workpackage  WP2 - Network Design and deployment

 

Objectives

·         To identify and compare transition strategies from IPv4 to IPv6.

·         To characterise existing access network technologies, selecting the most appropriate ones for trials integration regarding the IPv4 to IPv6 transition, support of required services and partners facilities.

·         To co-ordinate the specification, set-up and operation of the international required connections and guarantee the establishment of the required access from local research networks to the international connections.

·         To identify, evaluate and deploy solutions for advanced IP services, such as end-to-end QoS, multicast, mobility and security, in order to support collaborative work applications operation.

·         To design and deploy a Next Generation Telecommunications Network.

Deliverable No

 

 

Deliverable title

Delivery date

 

Nature

Dissemination level

D2.1

Description of IPv4/IPv6 available transition strategies

 

M06

 

R

 

PU

D2.2

Access Technologies in LONG project

M12

R

PU

D2.3

Advanced Network Services: description and support in LONG network

M14

R

PU

D2.4

Network Design and Deployment

M18

R

PU

 

 

 

1

Workpackage  WP3Collaborative Work Environment

 

Objectives

·         To define requirements and procedures for migration of applications to the new generation networks

·         To determine the requirements on the new generation network of advanced collaborative applications

·         Select and adapt representative collaborative work applications to new IPv6 and transition scenarios, including network scenarios with asymmetric links

Deliverable

Deliverable title

Delivery date

 

Nature

Dissemination level

D3.1

Requirements and guidelines for distributed laboratories application migration

M6

R

PU

D3.2

Guidelines for migration of collaborative work applications

M12

R

PU

D3.3

Guidelines for migration of collaborative work application working over asymmetric channels

M18

R

PU

 

 

1

Workpackage WP4 - System Exploitation, Trials and Evaluation

 

Objectives

·         Identify trials and experiments to provide feedback on the functionality and performance of the network.

·         Perform trials and experiments, performing measurements and collecting data during each experiment.

·         Provide guidelines on network configuration and design, based on the analysis of the processed data.

 

Description of work

The last phase of the project includes an evaluation of the tailored collaborative work applications (WP3) over the high performance network infrastructure deployed in the WP2.  For this purpose, LONG will perform trials in two phases First phase will include local tests of the core networking prototype of each institution. Second phase will include several distributed events with real end users. One of this trial will consist of a Workshop on the area of IPv6 and transition strategies IPv4/IPv6.

 

Deliverable No

Deliverable title

Delivery date

(month after start)

Nature

Dissemination level

D4.1

First phase trials scenario specifications.

M8

R

PU

D4.2

Report on first phase trials and evaluation report

M12

R

PU

D4.3

Second phase trials specification

M15

R

PU

D4.4

Conclusions and Guidelines from experiments.

M24

R

PU

 

 

1

Workpackage WP5 - Dissemination and Implementation

 

Objectives

·         Promote external dissemination of the results.

·         Maintain collaboration links with other projects working in the same area.

·         Participate in international fora related with new and emerging technologies.

·         Contribute to standardisation bodies and technology promoting organisations.

·         Submit papers to international conferences and relevant journals.

·         Maintain the web site of the project.

Deliverable No

Deliverable title

Delivery date

(month after start)

Nature

Dissemination level

D5.1

Dissemination and Use Plan

M6

R

PU

D5.2

Web site of the project for internal use including the relevant documents of the project

M6

O

RE

D5.3

Public Web site with general information about the project and related topics and projects

M8

O

PU

D5.4

Publication of the contributions to the Workshop and/or other dissemination events

M22

R

PU

D5.5

Final version of the Web site including all the planning, set-up and results of the experiments along with the guidelines and recommendations

M24

O

PU

 

Deliverable List

Deliverable List


Del. no.

Deliverable name

WP no.

Lead participant

Estimated person-months

Del. type*

Security**

Delivery

 

D1.1

Guide of project management and comm. Facilities

WP1

TID

1

R

Int.

M3

D1.2

Progress reports

WP1

TID

1

R

Int.

M3,6..21

D1.3

Summary of extensive conclusions and guidelines

WP1

TID

1

R

Pub

M22

D1.4

Final summary of conclusions and guidelines

WP1

TID

1

R

Pub

M26

D1.5

Final report

WP1

TID

1

R

Pub

M26

D2.1

Description of IPv4/IPv6 available transition strategies

WP2

PTIN

1

R

Pub

M06

D2.2

Access Technologies in LONG project

WP2

PTIN

1

R

Pub

M12

D2.3

Advanced Network Services: description and support in LONG network

WP2

PTIN

1

R

Pub

M14

D2.4

Network Design and Deployment

WP2

PTIN

1

R

Pub

M18

D3.1

Requirements and guidelines for distributed laboratories application migration

WP3

UPM

1

R

Pub

M6

D3.2

Guidelines for migration of collaborative work applications

WP3

UPM

1

R

Pub

M12

D3.3

Guidelines for migration of collaborative work application working over asymmetric channels

WP3

UPM

1

R

Pub

M18

D3.2A

New release of D3.2 (requested in 5/April/2002 Audit)

WP3

UPM

1

R

Pub

M19

D4.1

First phase trials scenario specifications.

WP4

UC3M

1

R

Pub

M8

D4.2

Report on first phase trials and evaluation report

WP4

UC3M

1

R

Pub

M12

D4.3

Second phase trials specification

WP4

UC3M

1

R

Pub

M15

D4.1A

New release of D4.1 (requested in 5/April/2002 Audit) with description of used methodology

 

WP4

UC3M

1

R

Pub

M19

D4.4

Conclusions and Guidelines from experiments.

WP4

UC3M

1

R

Pub

M25

D5.1

Dissemination and Use Plan

WP5

UPC

1

R

Pub

M6

D5.2

Web site of the project for internal use including the relevant documents of the project

WP5

UPC

1

O

Res

M6

D5.3

Public Web site with general information about the project and related topics and projects

WP5

UPC

1

O

Pub

M8

D5.4

Publication of the contributions to the Workshop and/or other dissemination events

WP5

UPC

1

R

Pub

M24

D5.5

Final version of the Web site including all the planning, set-up and results of the experiments along with the guidelines and recommendations

WP5

UPC

1

O

Pub

M26

 

* A short, self-evident description e.g. report, demonstration, conference, specification, prototype…

 

**Int.     Internal circulation within project (and Commission Project Officer if requested)

  Rest.                Restricted circulation list (specify in footnote) and Commission PO only

  IST                Circulation within IST Programme participants

  FP5                Circulation within Framework Programme participants

  Pub.     Public document

 